India’s atomic energy plan is entering Stage II, because the sodium-cooled PFBR (500 MW) in Kalpakkam, Tamil Nadu is close to commissioning. It bridges to the thorium stage that Homi Bhabha outlined in 1954.

Key facts

  • Builder: BHAVINI (set up 2003); design by IGCAR, Kalpakkam.
  • Fuel: plutonium-uranium MOX made from spent PHWR fuel; coolant: liquid sodium.
  • Core loading began 4 March 2024; AERB cleared fuel loading and first criticality approach in July 2023.
  • DAE’s timeline: criticality in 2025-26, complete commissioning by September 2026.
  • Predecessor: 40 MWt Fast Breeder Test Reactor (1985); two more 600 MW fast units are planned there.

The three stages

StageReactorFuel and role
IPHWRNatural uranium; heavy water moderator and coolant; e.g. Rawatbhata, Kaiga, Kakrapar
IIFast breederPlutonium from PHWR spent fuel; blanket of U-238 and thorium breeds more plutonium and U-233
IIIThorium reactorsU-233 from thorium, e.g. Advanced Heavy Water Reactor; India holds about 25% of world thorium
  • Kudankulam’s Russian VVERs are light water reactors and fall outside this line.

Roadmap

  • Installed: about 8.18 GW; 7.30 GW under construction; 7 GW pre-project; goal 22.48 GW by 2031-32.
  • Long-term aim of about 55 GW: 15.40 GW PHWRs, 17.60 GW light water reactors with foreign help, 3.80 GW fast breeders, plus SMRs and Bharat Small Reactors.
  • Nuclear Energy Mission (Budget 2025-26, ₹20,000 crore): 100 GW by 2047, five indigenous SMRs by 2033, and amendments to the Atomic Energy Act and Civil Liability for Nuclear Damage Act for private entry.

Significance

  • Closed fuel cycle multiplies energy from limited uranium.
  • Energy security, clean baseload power and near-complete self-reliance.

Exam angle

  • Breeder: makes more fissile material than it consumes; sodium is used since it does not slow neutrons but reacts violently with water and air.
  • Stage order: PHWR, then FBR, then thorium.

Test yourself

1. The 500 MW Prototype Fast Breeder Reactor is located at which place in Tamil Nadu?

The PFBR is at Kalpakkam, built by BHAVINI.

2. Which fuel and coolant does the PFBR use?

PFBR uses MOX fuel with liquid sodium coolant.

3. What is the order of India's three-stage nuclear programme?

Stage I is PHWR, Stage II fast breeder, Stage III thorium.