RBI Project Finance Provisioning Norms from October 2025
Why in the news
RBI finalised how much banks and NBFCs must set aside for loans to projects under construction. Rating agencies and lenders disliked the uniform rate.
Key facts
- Guidelines released 19 June 2025; effective 1 October 2025, new projects only.
- Framework is principle-based for stress resolution and allows flexibility in extending the DCCO (date of commencement of commercial operations).
- Same rates apply to MSMEs and small housing developers.
| Category | General provision in construction |
|---|---|
| Commercial Real Estate (CRE) | 1.25% |
| CRE – Residential Housing (CRERH) | 1.0% |
| All other projects | 1.0% |
Concerns
- Not linked to each project’s credit risk, unlike rating-based capital rules for corporate loans.
- MSMEs and small housing projects hit hardest, so lending may shrink.
- Higher capital cost could be passed on, making infrastructure finance dearer.
- Sectors with different risk and loss-given-default are treated alike.
Exam angle
- Rates: 1.25% CRE; 1.0% CRERH and others.
- Expand DCCO and CRERH.