India’s Renewable Energy Hurdles: 40 GW Unsold Capacity
Why in the news
India looked set to miss the 10 February deadline for its next climate action plan under the Paris Agreement, as renewable energy expansion ran into roadblocks.
Key challenges
- No power sale agreements: 40 GW tendered by SECI, NTPC, NHPC and SJVN remains unsigned, and state governments are reluctant to buy.
- Falling prices: solar at about ₹2.50 per unit is the cheapest power, but state electricity boards avoid long-term deals as each auction brings lower prices. TERI and the Climate Policy Initiative expect ₹1.9 per unit by 2030.
- Regulatory setback: SECI’s failure to sign PPAs led CERC to reject tariff approval for the first grid-scale battery energy storage system (BESS) tender.
- Coal reliance: without efficient storage, the variable nature of renewables keeps coal essential for reliable supply.
Impact on climate goals
- The 500 GW non-fossil capacity target for 2030 looks hard to meet for structural reasons.
- Missing agreements, stalled investment and coal dependence slow the low-carbon shift.
Exam angle
- Related terms: PSA, PPA, BESS, CERC, SECI.
- Target: 500 GW non-fossil capacity by 2030.